Carroll County Towns Take Different Approach With Sewer Projects

Two Carroll County cities have taken different directions toward upgrading their wastewater treatment plants.

The Green Forest City Council voted to abandon plans for a $6 million upgrade to the treatment facility for that city. The city has spent more than $500,000 in engineering fees with two firms in pursuit of plant improvements.

Mayor Charlie Reece who suggested abandoning the upgrade project said a USDA grant is available to pay 75% of the cost of a sludge press. The council action was unanimous.

In Berryville a contract was signed with a Rogersville, MO, firm to upgrade that city’s plant including installation of a sludge press and implementation of a new process to reduce the phosphorus produced.

The $3 million project is expected to be completed in 365 working days.